FOR more than four decades, the sprawling grounds of the Ajaokuta Steel Company have stood as a haunting monument to stalled ambition. Once envisioned as the furnace that would power Nigeria’s industrial revolution, the vast complex today tells a different story. It is a story of silent blast furnaces, weed-choked rail tracks, corroded pipes and warehouses filled with ageing, dust-coated machinery.
Commissioned in 1984 with an installed capacity of 1.3 million metric tonnes per annum, Ajaokuta Steel was designed to anchor heavy industry in Nigeria, feeding construction, automotive assembly, rail development and manufacturing. Instead, the plant has remained largely non-operational for decades, crippled by legal disputes, policy reversals and controversial concession agreements that left critical components idle.

Sections of the facility that once buzzed with promise now sit exposed to the elements. Steel structures bear the scars of oxidation. Control panels installed in the 1980s reflect outdated technology. Conveyor systems that were meant to transport iron ore from Itakpe lie still, symbols of a supply chain that never fully synchronised with production. What was conceived as Africa’s largest integrated steel complex has, for years, functioned more as an industrial relic than a productive asset.
Chinese investors
Yet the Nigerian government says that may soon change. Authorities have advanced negotiations with Chinese investors under a proposed $2 billion rehabilitation plan structured around a production-sharing model rather than an outright sale. The goal is not only to restart the moribund rolling mill but to scale output dramatically — from its original 1.3 million metric tonnes to as much as 10 million metric tonnes annually after stabilisation.
READ ALSO: Under Buhari and Tinubu, Ajaokuta Steel staff get N42bn as salaries without working
Director-General and Global Liaison for the Nigeria-China Strategic Partnership, Mr Joseph Tegbe, disclosed that the current administration of Bola Ahmed Tinubu is determined to unlock Ajaokuta’s long-dormant capacity, according to BusinessDay.
Nigeria currently consumes an estimated 10 million metric tonnes of steel each year but produces only about 1.2 million metric tonnes locally, most of it derived from recycled scrap rather than virgin iron ore. Tegbe argued that such reliance on scrap is unsustainable, especially given Nigeria’s significant iron ore deposits in Itakpe and parts of Kogi and Niger States.
After engaging nearly 10 Chinese firms, the government identified a preferred investor that conducted a two-week technical evaluation of the plant, deploying about 20 engineers at its own expense. Their findings indicated that while much of the equipment requires modernisation, the core infrastructure and structural framework remain viable.
Under the proposed arrangement, the Chinese partner would raise the $2 billion investment independently, subject to approval from China’s National Development and Reform Commission (NDRC). In return, the investor would recover funds through a sliding-scale production-sharing formula.

Nigeria would retain ownership of Ajaokuta. Initially, the investor could receive between 60 percent and 70 percent of output as repayment. Over a five- to 10-year period, that share would gradually decline to zero, after which Nigeria would assume full production control.
“They are not going to own Ajaokuta. Nigeria still owns Ajaokuta. What we are doing is production sharing,” the newspaper quoted Mr Tegbe as saying.
Mr Tegbe maintained that restarting even the existing rolling mill within six months of agreement would signal a symbolic and practical turning point.
The revival plan also addresses long-standing structural weaknesses. Past decisions to separate iron ore assets from the steel complex created supply bottlenecks that undermined efficiency. The government is now working to integrate the Itakpe iron ore source with Ajaokuta under a coordinated holding framework involving the Ministry of Steel Development and plant management.
Beyond the plant itself, discussions include upgrading supporting infrastructure, such as rail links from Warri Port through Itakpe to Ajaokuta, improvements to road corridors, inland waterways and dredging of Warri Port to accommodate larger vessels. Officials stress that steel production requires a seamless logistics ecosystem.
Technology transfer forms another pillar of the talks. Hundreds of Nigerian engineers are expected to undergo specialised training in China to ensure sustainable operations and local capacity building once the plant resumes activity.
Bilateral trade between Nigeria and China currently stands at about $23 billion, with only around $2 billion representing Nigerian exports. The government aims to expand total trade to $40 billion within five years while boosting Nigerian exports to at least $15 billion, anchored on value-added production such as steel.
Perennial budgets
The Nigerian government has persistently budgeted billions for Ajaokuta Steel. This year, the government plans to spend N6.7 billion on the moribund plant.
READ ALSO: Ajaokuta staff get N4.3bn package despite shutdown of steel complex
President Muhammadu Buhari appropriated N32.63 billion for the dormant steel plant in his 8-year tenure, yet it did not produce a single sheet of steel. Under Buhari, Nigeria wasted its scarce resources on the settlement of the bankrupt Global Steel Holdings to the tune of $496 million.
Unnamed consultants for the steel complex got N853 million for a proposed concession, which never happened. Yet steel importation into Nigeria rose over the period.
The Chief Executive Officer of Centre for the Promotion of Private Enterprise, Dr Muda Yusuf, who worked in the steel plant in the past, said political interference and corruption had stalled the progress of the plant.
“Right now, what we need to do is to unbundle the plant. It is so huge, so we may need to unbundle it to separate various sections such as the machine section, the technical section, the power plant and others. After doing that, get the private sector – a competent company- to manage it,” he added.